Caldwell Place Culvert Completion to be Delayed Until August
Patricia Chen · Union County Life
The Caldwell Place culvert project in Springfield has been extended due to additional drainage upgrades identified during construction. The roadway is now scheduled to reopen on Monday, August 3, 2026.
Springfield Township Committeeman Chris Capodice announced in a public release that Union County engineers determined more work was needed to prevent future ponding and winter icing along the roadway. The added work was not part of the original project plan.
"The county identified the need for two new storm drainage basins on the Mountain Avenue side of the culvert while construction was underway," Capodice said.
Capodice called the additional work "the right decision" for long-term safety and maintenance. He stated that addressing the drainage now is preferable to reopening the roadway and then having to address the problem later.
Union County Life covers public works projects, infrastructure updates, and municipal news across all 21 Union County municipalities, including Springfield construction projects.
As of Capodice's announcement, the new drainage structures were being installed. Curbing has been completed in several areas. Paver installation was scheduled for the following week.
The committeeman acknowledged that weather or other unforeseen conditions could affect the August 3 completion date, but stated the date reflects the latest information provided by Union County.
Residents should monitor Springfield Township announcements for updates on project progress and any further changes to the completion timeline.
More information about the Caldwell Place project can be obtained from the Springfield Township office or Union County.
Stay informed about Springfield public works and infrastructure projects on Union County Life.
FAQQ: When will the Caldwell Place culvert project be completed?
A: The project is scheduled to be completed and the roadway reopened on Monday, August 3, 2026. Weather or other unforeseen conditions could affect this schedule.
Q: Why has the Caldwell Place culvert project been delayed?
A: Union County engineers determined that additional drainage work was needed to prevent future ponding and winter icing along the roadway. Two new storm drainage basins were identified as necessary on the Mountain Avenue side of the culvert.
Q: Were the new drainage upgrades part of the original project plan?
A: No. The new drainage structures were identified during construction and were not part of the original plan. They represent added work that extended the project timeline.
Q: What work has been completed so far?
A: The new drainage structures are being installed. Curbing has been completed in several areas. Paver installation was scheduled for the week following the announcement.
Q: Is the August 3 date firm?
A: Committeeman Chris Capodice stated that weather or other unforeseen conditions could affect the August 3 completion date. The date reflects the latest information from Union County.
Q: Why is the additional drainage work important?
A: According to Capodice, the additional drainage work is "the right decision" for long-term safety and maintenance. Addressing the drainage now prevents having to reopen the roadway later to address ponding and icing issues.
Q: How can I get updates on the Caldwell Place project?
A: Monitor Springfield Township announcements and the township website for project updates. Contact the Springfield Township office or Union County for more information.
Q: What is being done to the Caldwell Place culvert?
A: Union County is replacing the culvert and upgrading the drainage system. The complete project includes installation of storm drainage basins, curbing, and paving.