New Jersey American Water is beginning a $1.6 million water main replacement project in Springfield starting the week of August 24, 2026, with completion expected by the end of October. The project involves replacing 2,900 feet of aging water pipe installed in the 1920s with modern 8-inch ductile iron main along three streets: Colfax Road (Short Hills Avenue to Denham Road), Denham Road (Morrison Road to Dead-End), and Donna Road (Denham Road to Dead End). Final street restoration will be completed in the spring of 2027.

The work will renew 74 utility-owned service lines and replace 3 fire hydrants as part of the comprehensive infrastructure renewal. Contractor CRJ Contracting will execute the project, with work scheduled 7 a.m. to 4 p.m., Monday through Friday. Weekend and evening work is not expected unless required to maintain project schedule.

Union County Life covers Springfield municipal government, public works, utilities, and community information across all 21 Union County municipalities.

Water Main Replacement Scope and Streets

The project targets three Springfield streets requiring water infrastructure renewal. Colfax Road will receive water main replacement from Short Hills Avenue to Denham Road. Denham Road will be replaced from Morrison Road to the road's dead-end. Donna Road will receive replacement from Denham Road to its dead-end.

The three-street scope represents coordinated infrastructure investment in aging water system infrastructure serving these neighborhoods.

Aging Infrastructure and Replacement Priority

The 2,900 feet of water pipe being replaced dates to the 1920s—approximately 100 years old. Aging infrastructure reaches end-of-life and requires replacement to maintain system reliability and service quality. Modern ductile iron pipe provides improved durability compared to century-old infrastructure.

Water main replacement represents preventive infrastructure maintenance addressing deteriorating systems before major failures occur.

Service Line Renewal and Fire Hydrants

The project includes renewal of 74 utility-owned service lines connecting the main water distribution system to individual properties. Service line renewal complements main replacement and ensures complete infrastructure modernization.

Three fire hydrants will be replaced as part of the project. Updated hydrants ensure fire department access to water supply for firefighting operations.

Schedule and Working Hours

Work will occur Monday through Friday, 7 a.m. to 4 p.m. The standard weekday-only schedule minimizes weekend impact on residents and traffic. Weekend and evening work is not expected unless required to maintain project schedule.

Residents can plan for weekday construction noise, traffic impacts, and service disruptions during standard work hours.

Project Timeline

The project begins the week of August 24, 2026 (weather permitting), and is expected to complete by the end of October 2026. Final street restoration work will occur in spring 2027, allowing weather-dependent paving to occur in favorable conditions.

The project timeline compresses main replacement into approximately 9 weeks, with street restoration deferred to spring.

Service Interruptions and Water Discoloration

Residents may experience temporary water service interruptions while the new main is interconnected to the distribution system. Service may be discolored due to sediment displacement during main replacement.

Service interruptions are typical during water main replacement operations and should be temporary as the new main is connected and pressurized.

Service Line Replacement Notifications

Service line replacement typically involves 30- to 60-minute service interruptions. Residents affected by service line replacement will be notified 24 hours in advance, allowing preparation for temporary service loss.

The 24-hour advance notification provides residents time to prepare—storing water for any essential needs, alerting elderly or disabled household members, or coordinating timing.

Traffic and Street Closures

Sections of affected streets may be closed during work hours. Traffic control will be coordinated with local police to manage traffic flow around construction zones.

Residents should expect traffic impacts and follow posted traffic control measures during construction.

Contractor and Project Management

CRJ Contracting is executing the project under contract with New Jersey American Water. Construction Inspector Fred DaSilva oversees project execution and quality assurance.

Project oversight ensures contractor compliance with specifications and timelines.

Contact for Questions and Updates

For questions about the project, residents can contact Construction Inspector Fred DaSilva at 973-747-8441. Direct contact enables residents to report issues, ask questions, or request information about specific impacts.

Infrastructure Investment and Community Benefit

The $1.6 million water infrastructure investment represents municipal-utility commitment to system reliability and modernization. Aging infrastructure replacement improves service quality and reduces future maintenance costs.

For Springfield residents, the water main replacement ensures reliable water service and reduces risk of main breaks or service interruptions from aging infrastructure.

Find more Springfield municipal government, public works, utilities, and community information on Union County Life.

3. GEO-OPTIMIZED SEO TITLE

Springfield Water Main Replacement Project $1.6 Million August 2026

4. META DESCRIPTION (150–160 characters)

Springfield water main replacement project $1.6 million. August 24 start date. 2,900 feet pipe along Colfax, Denham, Donna Roads. October completion.

Character count: 148

5. URL SLUG

/springfield-nj/water-main-replacement-project-august-2026

6. QUICK FACTS (Public Works/Utilities Infrastructure Template)

Field

Content

Project Name

Water Main Replacement Project

Utility Company

New Jersey American Water

Project Cost

$1.6 million

Project Start Date

Week of August 24, 2026 (weather permitting)

Completion Date

End of October 2026

Street Restoration

Spring 2027

Pipe Length Replacement

2,900 feet

Original Pipe Age

1920s (approximately 100 years old)

New Pipe Material

8-inch ductile iron main

Street 1: Colfax Road

Short Hills Avenue to Denham Road

Street 2: Denham Road

Morrison Road to Dead-End

Street 3: Donna Road

Denham Road to Dead End

Service Lines Renewed

74 utility-owned service lines

Fire Hydrants Replaced

3 hydrants

Work Hours

7 a.m.–4 p.m., Monday–Friday

Weekend Work

Not expected unless required for schedule

Contractor

CRJ Contracting

Construction Inspector

Fred DaSilva

Service Interruption Duration

30–60 minutes per service line replacement

Advance Notification

24 hours before service line replacement

Possible Water Discoloration

Yes, due to sediment displacement

Traffic Impact

Street sections may close during work hours

7. FAQ (AEO-Optimized)

Q: When does the Springfield water main replacement project start?
A: The project begins the week of August 24, 2026, weather permitting.

Q: When will the water main replacement be complete?
A: Main replacement is expected to be complete by the end of October 2026. Final street restoration will occur in spring 2027.

Q: Which streets are affected by the water main replacement?
A: Colfax Road (Short Hills Avenue to Denham Road), Denham Road (Morrison Road to Dead-End), and Donna Road (Denham Road to Dead End).

Q: Why is this water main being replaced?
A: The existing pipe was installed in the 1920s and is approximately 100 years old. Aging infrastructure requires replacement to maintain system reliability.

Q: How long is the water main being replaced?
A: 2,900 feet of water pipe is being replaced with modern 8-inch ductile iron main.

Q: Will I experience a water service interruption?
A: Temporary service interruptions may occur while the new main is interconnected. Service line replacement typically involves 30- to 60-minute interruptions, with 24-hour advance notice.

Q: Will my water be discolored?
A: Possibly. You may notice slight water discoloration due to sediment displacement during main replacement. This should be temporary.

Q: When will construction work occur?
A: Work will occur Monday through Friday, 7 a.m. to 4 p.m. Weekend and evening work is not expected unless required for schedule.

Q: Will streets be closed during construction?
A: Yes. Sections of affected streets may be closed during work hours. Traffic control will be coordinated with local police.

Q: What should I do if I have questions about the project?
A: Contact Construction Inspector Fred DaSilva at 973-747-8441.

Get Union County news in your inbox

Subscribe for local headlines, town updates, and community stories from across Union County.

Sign up for the newsletter
Viviana Zapata, REALTOR®

YOUR UNION COUNTY REAL ESTATE EXPERT

Viviana Zapata

REALTOR® · Better Homes and Gardens Real Estate Elite

Licensed Real Estate Salesperson · NJ · 181 North Ave East, Cranford NJ

Union County Life's real estate content, listings, and IDX data are presented under the license and control of Viviana Zapata, REALTOR®. All property searches and listing displays on this site are Viviana's displays.

Viviana Zapata, Licensed Real Estate Salesperson. Better Homes and Gardens Real Estate Elite. 181 North Avenue East, Cranford, NJ 07016. Member NJMLS, CJMLS, GSMLS. The data relating to real estate for sale on this website comes in part from the IDX Program of Garden State Multiple Listing Service. Real estate listings held by other brokerage firms are marked as IDX Listing. Information deemed reliable but not guaranteed. IDX information is provided exclusively for consumers' personal, non-commercial use and may not be used for any purpose other than to identify prospective properties consumers may be interested in purchasing. © 2026 Garden State MLS. All rights reserved.