Tatlock Playground Renovation Project Moves Forward with Design and Funding Plan
UCL Community Desk · Union County Life
The City of Summit is moving forward with a major renovation of Tatlock Playground, one of four city-owned playgrounds in Summit. In June 2022, Suburban Consulting Engineers delivered a playground assessment recommending a $1.3 million investment for Tatlock. The playground's design theme has been established as "nature."
The project has progressed through several phases. In Spring 2024, Summit Public Schools IDEAS classes worked on design concepts. In Fall 2024, a survey was sent via DCP communication outlets and Washington School PTO newsletter to gather feedback on the design ideas. In November and December 2024, the city met with playground providers, and in January 2025, cost estimates and renderings were requested from Kompan, the selected playground equipment provider.
Two options for the project have been developed. Option A costs $1,315,295.65, while Option B costs $1,043,294.55. Current funding totals $852,000, including $250,000 from the 2024 Capital Budget, $500,000 from a pending 2025 Capital Budget request, $40,000 from a 2024 Kids Recreation Trust Grant from Union County, and $62,000 from a 2024 Local Recreation Improvement Grant from the State. Remaining fundraising goals are $191,294.55 for Option A or $463,295.65 for Option B.
The project timeline indicates a fundraising campaign from March through July 2025, with a contract for specialized Owl and Tree Play structures targeted for May 2025 due to a seven-month lead time. Full equipment purchase contracts are scheduled for September 2025, with construction planned for November and December 2025. Kompan equipment is available through a State Contract, with installation managed through a Bergen County Co-op arrangement.
This article was produced with AI assistance and reviewed for accuracy against official sources.
Produced with AI assistance and reviewed against source records.
Related articles
New Providence to Open Oakwood Park Playground on Sept. 1
New Providence held grand opening of Oakwood Park Playground September 1. Funded by Jake's Law Playground Grant and Union County Kids Recreation Trust Fund.
Parks & RecreationCity of Plainfield Pool Update
Plainfield announces this weekend closures at Hannah Atkins Pool and the main Rushmore Aquatics Complex pool due to unavoidable circumstances. Splash Park only is open.
Green Lane Park Reopens in Union Township After $3.6M Renovation
Union Township's Green Lane Park has reopened after a $3.6 million renovation that added a nature-based playground, boardwalk, walking trails, and more to the five-acre site.
Get Union County news in your inbox
Subscribe for local headlines, town updates, and community stories from across Union County.
Sign up for the newsletter